Dhanbad: File of revised estimate of Rs 40 crore reached cabinet, hope increased for completion of eight lane work.

Dhanbad: The file of revised estimate of eight lanes has reached the cupboard. After getting the approval from the cupboard, there will likely be an settlement on the revised estimate with Shivalay Building and Triveni Building, the 2 corporations doing the work of eight lanes. With this, utility shifting of eight lanes, highway furnishings and incomplete drain and highway work will likely be accomplished. Each the businesses have gotten extension 4 occasions. The deadline to finish the work is thirty first December. In such a scenario, these corporations are certain to get extension for the fifth time.

Work has stopped for 15 days: Resulting from lack of settlement on the revised estimate of Rs 40 crore, each the businesses Shivalay Building and Triveni Building have stopped work for 15 days. The contractors are saying that the work will begin after the revised estimate will get approval from the cupboard. He says that some huge cash is caught within the eight lane challenge. In such a scenario, additional work is just not attainable.

JUDCO has made an extra estimate of Rs 85 crores

Allow us to inform you that the tender for development of eight lane highway was given for Rs 332 crore. Later the expenditure elevated as a result of improve in costs of products and addition of some new works of utility shifting. Because of this, JUDCO made an extra estimate of Rs 85 crore, but it surely has not but acquired the approval of the federal government. Nevertheless, the file has reached the cupboard. It’s hoped that the unfinished work will likely be accomplished within the subsequent two months.

Accidents taking place as a result of avenue lights not working

Resulting from Rs. 40 lakh, the road mild put in on the eight lane highway is just not getting electrical connection. The revised estimate additionally contains electrical energy connection. Resulting from non-functioning of avenue lights, accidents are taking place day by day on the eight-lane highway.

Dhanbad: Prepare operations badly affected as a result of dense fog

Click Here To Join Our Telegram Channel

In case you have any considerations or complaints relating to this text, please tell us and the article will likely be eliminated quickly.Β 

Raise A Concern

Show More

Related Articles

Back to top button